AUREUS PRIMARY SCHOOL



Project: AUREUS PRIMARY SCHOOL
Subject: DISPUTE RESOLUTION REPORT
Value: Infrastructure & Earthworks Package Value: £500k
Area: Specialist Commercial & Technical Consultancy Services
Client: Due to the sensitive nature of our work we do not reveal the name of our client
Achievements: Successfully protected and promoted the interests of our client
Main deliverables:
-
Settled clients dispute against designer and contractors
-
Earthwork Models Preparations in Software
-
Final Account Assessment with the assessment of all associated change
Work Items
Phase 1
-
Review opposition’s party technical note
-
Interrogate opposition’s party survey and compile associated models
-
Compile additional models that account same conditions with those considered by the opposition party and examine their validity and behaviour.
-
Review existing survey data and compile its model
-
Review Clients as-build drawings and models as required
-
Run all necessary surface comparisons, extract and study results
-
Create isopachyte drawings for all the surface model comparisons – isopachyte drawings to also include grid with +/- clearly measured as required.
-
Calculate separately the volume of the disputed area and supply all different versions of results based on the available data.
-
Model all ‘’additional Surveys’’ that are held within file and examine whether there are any items of interest
-
Compare ‘’additional Surveys’’ against all other data
-
Extract, Study and Explain all relevant results
-
Write Technical Note with Recommendations
Phase 2
-
Calculate full Cut and Fill volume and compile all relevant drawings and models to support clients’ position
-
Compile Report that Responds to Opposition Party in support of Clients position
-
Agree and settle the dispute